MONITORING AND CONTROLLING ON SURFACE SETTLEMENT IN SAND AND GRAVEL STRATA CAUSED BY SUBWAY STATION CONSTRUCTION APPLYING PIPE-ROOF PRE-CONSTRUCTION METHOD (PPM)

Autoři

  • Xian Yang School of Resource, Environment and safety Engineering, Hunan University of Science and Technology, Xiangtan, 411201, China
  • Yang Liu Key Laboratory of Metallogenic Prediction of Nonferrous Metals and Geological Environment Monitoring (Central South University), Ministry of Education, Changsha, Hunan, 410012, China

DOI:

https://doi.org/10.14311/CEJ.2017.02.0016

Klíčová slova:

Pipe-roof Pre-construction Method (PPM), Pipe jacking, large-scale excavation,Surface settlement

Abstrakt

Pipe-roof Pre-construction Method (PPM) is regarded as a safer method to construct underground space, especially suitable for the construction sites with dense surface buildings, underground pipelines and complicated geological conditions. Xinleyizhi Station of Shenyang Metro constructed by PPM. In order to ensure safety in construction, the whole construction process was closely monitored. In this paper, monitoring results of surface settlement in PPM is analyzed. According to the monitoring results, the most serious settlement occurred in pipes jacking, which was the first and the most crucial step in PPM. The settlement reasons in each step are discussed, and controlling methods of surface settlement in each step are elaborated. Through close monitoring and timely control, the construction of Xinleyizhi Station completed smoothly. Because of the obvious advantages of PPM, the method will be used more widely in construction of shallow buried excavation under complicated surrounding and geological conditions.

Stažení

Data o stažení nejsou doposud dostupná.

Reference

Musso G, 1979.Jacked Pipe Provides Roof for Underground Construction in Busy Urban Area. Civ Eng 49(11):79-82.

Hemerijckx E,1983. Tubular Thrust Jacking for Underground Roof Construction on the ANTWERP Metro Part 1.Tunn Tunn Int 15(5):13-16

Lunardi P, 1991.Cellular Arch Technique for Large-span Station Cavern. Tunn Tunn Int 23:23-26.

Kwak C W, Park I J, Kim S W, Kim J Y, 2007.Seismic behavior of Tubular Roof-Trench method(T.R.&T) by numerical analysis. 33rd ITA-AITES World Tunn Congr-Undergr Spac-The 4th Dim Metr 1: 513-518.

Li YS, 2011.Research of the construction mechanics effect during large excavation to the subway station built by Pipe-roof Pre-construction Method.Dissertation. Central South University.

Park IJ, Kwak C W, Kim S W, Kim J Y, Han S H ,2006. Verification and general behaviour of Tubular Roof & Trench method (TR&T) by numerical analysis in Korea.Tunn Undergr Sp Tech 21(3): 394-398.

Yan S, Zhang ZJ, Jin CF, Jing L, 2011. Numerical analysis on inner forces of underground New Tubular Roof structure during excavation. J Shenyang Jianzhu U 27(6):1064-1069

Li YS,Zhang KN,Huang CB ,2012. Monitoring of lining structure of tunnels built by using pipe-roof pre-construction method.Chin J Geotech Eng 34(8): 1541-1547.

Li YS, Zhang KN, Huang CB, Li Zh, Deng ML, 2011b. Analysis of surface subsidence of tunnel built by pipe-roof pre-construction method. Rock Soil Mech 32(12): 3701-3707

Yang X, Zhang KN,Li Z,2012a. Influence of steel pipe jacking on earth surface settlement in pipe roof pre-construction method[J]. J Shenyang U Tech 4: 469-473

Yang X, 2012b. Reasearch of Large Diameter Jacking-Pipes with Small Space in Pipe-roof Pre-construction Method.Dissertation. Central South University.

Yang X, Zhang K, Li Z, et al. Optimal design of distance between jacking pipes of new pre-construction method in Metro station[J]. China Railway Science, 2011, 32(2):61-66.

Stahování

Publikováno

2017-07-31

Jak citovat

Yang, X., & Liu, Y. (2017). MONITORING AND CONTROLLING ON SURFACE SETTLEMENT IN SAND AND GRAVEL STRATA CAUSED BY SUBWAY STATION CONSTRUCTION APPLYING PIPE-ROOF PRE-CONSTRUCTION METHOD (PPM). Stavební Obzor - Civil Engineering Journal, 26(2). https://doi.org/10.14311/CEJ.2017.02.0016