REDUCTION OF THE RISK IN PUBLIC PROCUREMENT BY USING DESIGN-BUILD AS A MEANS FOR SUITABLE CONSTRUCTING

Authors

  • Jakub Blaťák Czech Technical University, Faculty of Civil Engineering, Department of Economics and Management in Civil Engineering, Prague, Thákurova 7/2077, Czech Republic

DOI:

https://doi.org/10.14311/CEJ.2016.02.0007

Keywords:

design-build, public procurement, RIPRAN, design-build risks

Abstract

Suitable and sustainable buildings have increased demands for design and for the transfer of design requirements to realization. That causes an increase of risk connected with the differences between planned and real parameters of the buildings. This article will outline the main theme comparison between DBB and DB projects concerning contractor’s risk management level. This comparative analysis explains, using the RIPRAN method, the hidden risks in each type of delivery method. The comparison identifies numerous contractual topics and risks included in both and gives deeper insight into risk management, both for the contracting party and also for public procurement. Applying risk analysis strategies and tools to the process will help decision-makers evaluate and select the suitable delivery method consistently and defensibly. This paper gives generic risk factors related to both project types. The results indicate risk factors with influence on the price, probability of occurrence and unfavourable impact on the project and help allocate risk level more properly in accordance with its high, middle or low probable impact. Public investment is a significant part of the public budget, the application of design-build can help with the reduction of corruption, and the public sector can benefit from the usage of DB projects to help eliminate the mistakes made by contracting authorities.

Downloads

Download data is not yet available.

References

Chang, A., Shen, F. and Ibbs, W. Design and construction coordination problems and planning for design-build project new users. Canadian Journal of Civil Engineering, DOI: 10.1139/L10-090, 2010

Palaneeswaran, E., Kumaraswamy, M., and Ng, T. Targeting optimum value in public sector projects through “best value”-focused contractor selection, Engineering, Construction and Architectural Management, DOI: 10.1108/0969998310509390, 2003

RAMP. Risk Analysis and Management for Projects. ICE—Institution of Civil Engineers, Faculty of Actuaries, and Institute of Actuaries, London, 2004

Lam, K., et al. Modelling Risk Allocation Decision in Construction Contracts. International Journal of Project Management, 25, 485-493. DOI: 10.1016/j.ijproman.2006.11.005, 2007

ÖZTAŞ, Ahmet a Önder ÖKMEN. Risk analysis in fixed-price design–build construction projects. Building and Environment,39(2), 229-237, DOI: 10.1016/j.buildenv.2003.08.018. ISSN 03601323. 2004

AL-RESHAID, Khaled a Nabil KARTAM. Design–build pre-qualification and tendering approach for public projects. International Journal of Project Management, 23(4), 309-320, DOI: 10.1016/j.ijproman.2004.11.004., 2005

Lacko, B.: Aplikace metody RIPRAN v softwarovém inženýrství., In: Sborník celostátní konference TVORBA SOFTWARU 2001, VŠB Ostrava, Str.97 – 103 (ISBN 80-85988-59-3), 2001

Pavelková, M. – Korytárová, J.: Analýza rizik a nejistot projektu Moravian Science Centre Brno. Stavební obzor, 21, č. 10, s. 312-320. ISSN 1805-2576, 2012

JEŽKOVÁ, Zuzana, KREJČÍ Hana, LACKO Branislav. Projektové řízení Jak zvládnout projekty. Kuřim: Akademické centrum studentských aktivit, (ISBN 978-80-905297-1-7), 2014

PMBOK Guide, A Guide to Project Management Body of Knowledge (Fifth Ed.). Project Management, Institute, Pennsylvania, s. 310 - 320, ISBN 9781935589679, 2013

Edwards, L. Practical risk management in the construction industry, London, Thomas Telford, ISBN 0727733907, 1995

Flangan, R. Risk management and construction, Oxfor, Blackwell Science, ISBN: 0-632-02816-5, 1993

Alali, B. and Pinto, A. Project, systems and risk management processes interactions. Management of Engineering & Technology, DOI: 10.1109/PICMET.2009.5261999, 2009

Wang, S., Dulaimi, M. & Aguria, Y. Risk management framework for construction projects in developing countries. Construction Management and Economics, 22(3), 237-252, DOI: 10.1080/0144619032000124689, 2004

Tah, J. y Carr, V. Knowledge-Based Approach to Construction Project Risk Management. Journal of Computing in Civil Engineering, 15(3), 170-177, DOI: 10.1061/(ASCE)0887-3801(2001)15:3(170), 2001

Kamara, J., Augenbroe, G., Anumba, C., & Carrillo, M. Knowledge management in the architecture, engineering and construction industry. Construction Innovation: Information, Process, Management, 2(1), 53-67, DOI: 10.1108/14714170210814685, 2002

Forbes, D., Smith, S. & Horner, M. Tools for selecting appropriate risk management techniques in the built environment. Construction Management and Economics. 26, 1241-1250, DOI: 10.1080/01446190802468487, 2008

Downloads

Published

2016-07-31

How to Cite

Blaťák, J. (2016). REDUCTION OF THE RISK IN PUBLIC PROCUREMENT BY USING DESIGN-BUILD AS A MEANS FOR SUITABLE CONSTRUCTING. Stavební Obzor - Civil Engineering Journal, 25(2). https://doi.org/10.14311/CEJ.2016.02.0007